Robust Updated PEA Highlights Ashrams Potential
Released
Released
Announcement PDF
Level 8, 2 Bligh Street
Sydney NSW 2000
Mont Royal Resources Ltd
ACN: 625 237 658
E: info@montroyalres.com
www.montroyalres.com
ASX ANNOUNCEMENT
9th June 2026
Updated Preliminary Economic Analysis Confirms
Ashram as a Major Long-Life North American Rare
Earths Development Project
ROBUST UPDATED PEA HIGHLIGHTS ASHRAM’S POTENTIAL TO BECOME A
STRATEGICALLY IMPORTANT LONG-TERM SUPPLIER OF RARE EARTHS INTO
WESTERN CRITICAL MINERALS SUPPLY CHAINS
Cautionary Statement
The Preliminary Economic Assessment (PEA) is a preliminary technical and economic study of the potential
viability of the Ashram Rare Earths & Fluorspar Project. It is based on low-level technical and economic
assessments that are not sufficient to support the estimation of Ore Reserves or to provide assurance of an
economic development case at this stage, or to provide certainty that the conclusions of the PEA will be
realised. Further exploration, technical, and economic studies are required before the Company will be in a
position to estimate any Ore Reserves or to provide assurance of an economic development case. The PEA
has been completed to a level of accuracy of ± 50%.
Forward-Looking Statements
The PEA is based on the material assumptions outlined in this announcement. These include assumptions
about the availability of funding. While Mont Royal considers all of the material assumptions to be based on
reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes
indicated by the PEA will be achieved.
To achieve the range of outcomes indicated in the PEA, funding in the order of CAD$1.23 billion (initial
capital, excluding access road, including 30% contingency) will likely be required. Investors should note that
there is no certainty that Mont Royal will be able to raise that amount of funding when needed. It is also
possible that such funding may only be available on terms that may be dilutive to or otherwise affect the
value of Mont Royal's existing shares. It is also possible that Mont Royal could pursue other value realisation
strategies such as a sale, partial sale, or joint venture of the Project. If it does, this could materially reduce
Mont Royal's proportionate ownership of the Project.
There is a low level of geological confidence associated with Inferred Mineral Resources and there is no
certainty that further exploration work will result in the determination of Indicated Mineral Resources or that
the production target itself will be realised. Given the uncertainties involved, investors should not make any
investment decisions based solely on the results of the PEA.
Of the approximately 53 Mt of mill feed underpinning the 30-year production target, approximately 93% is
sourced from Indicated Mineral Resources and approximately 7% is sourced from Inferred Mineral Resources.
There is a low level of geological confidence associated with Inferred Mineral Resources and there is no
certainty that further exploration work will result in the determination of Indicated Mineral Resources or that
the production target itself will be realised.
The Inferred Mineral Resources do not feature as a significant proportion early in the mine plan. The mine
plan is sequenced such that Indicated Mineral Resources predominate in the early years of production, with
Inferred Mineral Resources weighted towards the later stages of the mine life. The Company is satisfied that
the respective proportions of Inferred Mineral Resources are not the determining factors in project viability.
2
HIGHLIGHTS1
• Updated Preliminary Economic Assessment (“PEA”) confirms the Ashram Rare Earths
Project (“Ashram” or the “Project”) in Québec, Canada, as a large-scale, long-life North
American rare earth development.
• Large-scale production profile:
o Average annual production of ~17,466 tonnes of saleable Rare Earth Oxide (REO)
o Average annual production of ~4,035 tonnes of Nd2O3 & Pr2O3 (NdPr)
▪ ~100 tonnes of Dy2O3 & Tb2O3 (DyTb)
▪ ~ 230 tonnes of Y2O3 (Y)
o Initial mine life of 30 years supported by a resource base that remains capable of further
expansion, with 93% of the resource schedule in the Indicated category.
o Base case utilises only 25% of the current global resource, highlighting significant
long-term expansion optionality
o Initial nameplate mill throughput of ~1.8Mtpa supporting a long-life open pit operation
with a low strip ratio of 0.4:1
• Robust project economics:
o Post-tax NPV8% (real) of CAD$2.03B
o Post-tax IRR (real) of 22.0% and post-tax payback of 3.9 years from commencement
of production
o Life of Mine (LOM) revenue of ~CAD$24.6B and a life-of-mine EBITDA margin of
~62.7%
o Initial CAPEX of ~CAD$1.23B, including 30% contingency, with access infrastructure
costs assumed under a contracted/shared logistics model and reflected in operating
expenditure
o The project is anticipated to benefit from ~CAD$342M of refundable Clean
Technology Manufacturing Investment Tax Credits (CTM ITC) incorporated into post-
tax cash flows
• Competitive cost position:
o C1 cash cost of approximately CAD$17.99/kg saleable REO
o AISC of approximately CAD$18.58/kg saleable REO
o Cost profile supported by low strip ratio, favourable mineralogy, production of a high-
grade rare earth concentrate and an integrated hydrometallurgical refining strategy
• Strategic project positioning:
o Ashram is one of the largest monazite-dominant rare earth deposits in North America
1
There is a low level of geological confidence associated with Inferred Mineral Resources and
there is no certainty that further exploration work will result in the determination of Indicated
Mineral Resources or that the production target itself will be realised. Refer to the cautionary
statement on page 1 of this announcement for further details.
3
o The Project offers exposure to a high-value magnet rare earth basket led by NdPr with
additional Dy and Tb content, and potential future fluorspar value upside
o Integrated development concept incorporates on-site concentration at Ashram and
downstream hydrometallurgical refining in Saguenay, Québec
o Located in Québec, one of the world’s leading mining jurisdictions
o Ashram is well positioned to support Western government and industry initiatives
aimed at establishing secure critical minerals supply chains outside China
• Additional value upside:
o Potential inclusion of a dedicated fluorspar recovery circuit in future studies
o Broader district exploration upside across additional targets within the Eldor
carbonatite complex, including satellite targets such as Mallard
o Potential future inclusion of higher-value zones, including the BD Zone, subject to
further test work and study
o Downstream and strategic partnership opportunities
o Opportunity to optimise road access costs. A regional shared infrastructure strategy is
being evaluated as a means of reducing access road costs through potential
collaboration with other mining projects, government agencies, and First Nations.
• Next steps:
o Progression toward a Pre-Feasibility Study (PFS), targeted to commence in H2 CY2026
o Ongoing metallurgical optimisation, engineering refinement, and workstreams to
further de-risk the flowsheet and development pathway
o Advancement of environmental baseline, permitting and stakeholder engagement
programs across both the Ashram and Saguenay development footprint
o Continued engagement regarding offtake, downstream and strategic partnership
opportunities
Mont Royal’s Managing Director, Mr. Nicholas Holthouse, said:
“The updated PEA marks a major step forward for the Ashram Project, confirming a large-scale, long-
life development with strong underlying economics and a clear pathway to advancement. The study has
highlighted Ashram’s combination of scale, favourable mineralogy and competitive cost profile,
supporting its potential to become a meaningful long-term supplier of rare earth products into Western
supply chains. Importantly, we see further upside beyond the base case, including opportunities in
fluorspar, resource expansion and downstream partnerships and collaboration.
This is a project that can have a meaningful and long-lived impact on the development of rare earth
industries and technologies within Quebec, Canada, North America and Europe.
Our focus now is continuing to work with First Nations and Government agencies on developing
infrastructures strategies and on progressing the project into pre-feasibility, advancing permitting and
continuing engagement with strategic and offtake partners.”
4
PRELIMINARY ECONOMIC ASSESSMENT OVERVIEW
Mont Royal Resources Limited (ASX: MRZ,TSXV: MRZL) (“Mont Royal” or the “Company”) is pleased
to present an updated Preliminary Economic Assessment (“PEA”) for its 100%-owned Ashram Rare
Earths and Fluorspar Project located in Nunavik, Québec, Canada.
The PEA was completed by Altris Engineering (“Altris”) in accordance with National Instrument 43-
101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) in collaboration with the following
specialist firms:
• Altris Engineering
• BBA Inc. (BBA)
• PLR Resources Inc. (PLR)
• DRA Americas Inc. (DRA)
• L3 Process Development (L3)
• ASDR Canada Inc.
• TALA Geotec
• Norda Stelo Inc.
The updated study incorporates significant optimisation work completed since prior economic
studies, including:
• revised mining and processing assumptions;
• optimisation of transportation and logistics pathways;
• incorporation of a proposed hydrometallurgical processing facility in Saguenay, Québec;
• updated infrastructure assumptions; and
• revised engineering and metallurgical inputs.
The PEA highlights the potential for Ashram to become a major long-term supplier of rare earth
products into Western and allied critical mineral supply chains.
Ashram is one of the largest monazite-hosted rare earth deposits in North America and contains a
favourable distribution of magnet rare earth elements, including neodymium and praseodymium
(“NdPr”), which are critical components used in EVs, permanent magnets, wind turbines, robotics,
semi-conductors, aerospace technologies and defence applications.
The Economic Summary and metrics for the project are shown below in TABLE 1 and TABLE 2.
TABLE 1: Updated PEA – Economic Summary
Economic Metrics Unit Value
LOM Revenue CAD M 24,638
LOM EBITDA CAD M 15,460
EBITDA Margin % 62.7%
LOM Undiscounted Post-Tax Cashflow CAD M 8,365
NPV8% Post-Tax (real) CAD M 2,026
NPV8% Pre-Tax (real) CAD M 3,440
IRR Post-Tax (real) % 22.0%
IRR Pre-Tax (real) % 25.6%
Post-Tax Payback years 3.9
5
TABLE 2: Operating cost profile
Unit Cost Metric Unit Value
C1 Cash Cost CAD/kg saleable REO 17.99
AISC CAD/kg saleable REO 18.58
PROJECT OVERVIEW AND HISTORY
The Ashram Project is located on Mont Royal Resources’ 100%-owned Eldor Property in Nunavik,
northern Québec, approximately 130km south of Kuujjuaq, and covers 11,475ha across 244
contiguous Exclusive Exploration Rights (EERs) as shown in Figure 1.
Figure 1: Ashram REE and Fluorspar Project location
6
The Project hosts the Eldor Carbonatite Complex, including the Ashram Rare Earth and Fluorspar
Deposit, with additional potential for niobium, tantalum and phosphate mineralisation.
Following the merger between Commerce Resources and Mont Royal Resources in October 2025,
the combined group consolidated ownership and strategic direction for the Project.
Commerce Resources Corporation holds a 100% interest in all EERs, which are in good standing
until May 2027. Importantly, the Ashram Deposit is not subject to the limited third-party royalties
applicable to a small number of original claims. The Property is fully permitted for exploration, with
no known material environmental, legal or access constraints.
The Project is accessible via Kuujjuaq, which serves as the primary logistics hub with regular air
services from Montréal and seasonal marine supply access. A permanent on-site exploration
facility, Camp Valcourt, supports year-round operations and accommodates up to 35 personnel.
The Project benefits from several strategic infrastructure advantages, including:
• access to established logistics corridors;
• proximity to potential port infrastructure;
• access to low-cost renewable hydroelectric power in Québec (Saguenay site);
• a supportive mining jurisdiction; and
• access to established industrial infrastructure in Saguenay.
Since acquiring the Property in 2007, Commerce has completed extensive drilling, geophysical
surveys, trenching and surface exploration programs.
The Ashram REE Deposit was discovered in 2009, with subsequent drilling confirming a large-scale,
continuous mineralised system extending from surface to depth.
This work supported the establishment of NI 43-101 compliant Mineral Resource Estimates, which
have since positioned Ashram as one of the largest undeveloped rare earth deposits in North
America.
GEOLOGICAL SETTING
Ashram is hosted within the Eldor Carbonatite Complex, a large intrusive carbonatite system
located within the Paleoproterozoic New Québec Orogen.
Rare earth mineralisation is dominated by monazite, with subordinate bastnäsite, parisite and
xenotime. The relatively simple and commercially favourable mineral assemblage is considered
advantageous for metallurgical recovery and downstream processing.
The deposit includes several mineralised zones, including:
• A-Zone;
• B-Zone;
• Breccia Zone; and
• BD-Zone.
These zones vary in texture and grade, with the A‑Zone hosting the highest and most continuous
REE grades. Niobium and tantalum mineralisation occurs elsewhere in the complex, mainly hosted
in pyrochlore‑group minerals within carbonatite and phoscorite units.
7
The relatively simple mineral assemblage is considered commercially favourable and comparable
to other major carbonatite-hosted REE systems globally, including Mountain Pass (USA), Niobec
(Québec) and Palabora (South Africa).
MINERAL RESOURCE ESTIMATE
The updated PEA uses the updated JORC MRE for the Ashram Deposit released on October 1,
2025 (Table 3). The Ashram MRE integrates drilling data collected between 2008 and 2022 and
was completed using industry‑standard geological modelling and geostatistical methods.
A total database of 213 drill holes, six surface channels, and nearly 33,000 samples underpin the
estimate, with mineralisation defined within three REE‑bearing domains (A‑Zone, B‑Zone, and
Breccia Classic). The drill hole collars are shown below in Figure 2.
Figure 2: Carbonatite Complex Geology of the Ashram Project.
8
Ordinary kriging was applied within a detailed 3D block model constrained by a conceptual
open‑pit shell developed to demonstrate reasonable prospects for eventual economic extraction.
The estimate is classified in accordance with CIM standards, defining Indicated and Inferred
Resources based on drill spacing, geological confidence, and grade continuity; no Measured
Resources are defined at this stage. The confidence categories assigned under the CIM Definition
Standards were reconciled to the confidence categories under the JORC Code, as disclosed in the
Company’s Prospectus released to ASX on 1 October 2025.
Interpreted zones are shown below in the cross-section in Figure 3 with Figure 4 showing the block
model coloured by resource classification within the resource shell.
Figure 3: Geological model cross-section of the Ashram Deposit, highlighting carbonatite lithological domains
considered in the MRE.
9
Figure 4: Cross-section showing Indicated and Inferred classifications within the block model.
Figure 5: Cross-section showing the TREO % distribution.
Using a base case, net metal return (NMR) cut‑off of CAD$287/t, the MRE defines 73.2 Mt of
Indicated Resources grading 1.89% Total Rare Earth Oxides (TREO) and 131.1 Mt of Inferred
Resources grading 1.91% TREO. The resource exhibits a favourable rare‑earth distribution, with
NdPr accounting for approximately 21% of TREO and meaningful contributions from the critical
heavy rare earths Tb and Dy with Figure 5 showing TREO distribution.
Mineralisation remains open laterally and at depth, and the estimated pit shell outlines a large,
continuous deposit with a conceptual strip ratio across the entire MRE of approximately 2.7:1.
10
Table 3: 2025 Ashram Project Mineral Resource Estimate
Cut-off NMR CAD $287 / tonne
Category Unit Indicated Inferred
Tonnes Mt 73.2 131.1
Total TREO
%
1.89 1.91
Nd+Pr Oxide/TREO 21.2 21.4
Dy+Tb Oxide/TREO 0.7 0.5
La2O3
ppm
4,829 4,969
Ce2O3 8,753 8,933
Pr2O3 907 927
Nd2O3 3,112 3,162
Sm2O3 412 385
Eu2O3 98 87
Gd2O3 223 195
Tb2O3 24 19
Dy2O3 102 73
Ho2O3 14 10
Er2O3 31 21
Tm2O3 3 2
Yb2O3 18 13
Lu2O3 2 2
Y2O3 419 280
Fluorspar (CaF2) % 6.6 4.0
(a) TREO is sum of lanthanides (as oxides) + yttrium oxide
(b) NdPr distribution calculated as (Nd2O3 + Pr2O3) / TREO x 100
(c) CaF2 calculated from fluorine assay using factor of 2.055 (F to CaF2). Assumes all fluorine is contained
within the mineral fluorite (“fluorspar”)
(d) Cut-off expressed as NMR ($)/t only considers payable elements La-Nd-Pr-Tb-Dy
(e) DyTb distribution calculated as (Dy2O3 + Tb2O3) / TREO x 100
(f) Prices shown are in CAD
(g) Differences may occur in totals due to rounding
The MRE confirms Ashram as a large, well-defined rare earth deposit with strong grade continuity
and favourable metallurgical characteristics. The BD-Zone, also an REE-bearing unit, was excluded
from the estimate pending further metallurgical evaluation and therefore represents additional
resource upside.
Overall, the MRE provides a solid basis for advanced technical studies and future resource
definition through continued drilling.
11
DEVELOPMENT PATHWAY
The updated PEA contemplates a mine and concentrator operation located at Ashram, with
production of an intermediate mixed rare earth concentrate (“MREC”) product for downstream
processing.
The Project development strategy incorporates:
• on-site concentration;
• multi-modal logistics transportation;
• hydrometallurgical processing in Saguenay;
• production of saleable mixed rare earth products; and
• future optionality for additional downstream processing initiatives.
The Company believes this approach:
• materially improves execution certainty;
• reduces development complexity;
• enhances scalability;
• supports financing pathways; and
• aligns with broader Québecois and Canadian critical minerals strategies.
MINING
The Ashram Project mine design and mine plan are based on a conventional open-pit, truck-and-
shovel operation using drill-and-blast mining on 10m benches, operated by an owner fleet on a
continuous 7-day, 12-hour shift basis.
While the Mineral Resource supports a theoretical 169-year mine life at 4,900tpd, a 30-year life-of-
mine (LOM) was adopted for the PEA as it captures most of the Project’s value. Based on technical
and economic parameters and metal selling prices, the Net Metal Return (NMR) cut-off for the
Project was calculated at CAD$88/t.
A trade-off study assessing the impact of higher cut-off values on Project economics and
concentrator feed quality resulted in the selection of an elevated cut-off strategy being adopted
and an NMR cut-off of CAD$217/t was ultimately selected for the PEA.
The resulting open pit design for the 30-year mine life includes 53 Mt of mill feed at a strip ratio of
0.4:1. Access to mineralisation beneath the shallow centre pond will require the construction of
dewatering dykes and controlled pond dewatering. Mine design, scheduling and cost estimation
were completed using MinePlan 3D software, supported by geological, topographical and material
property data.
Of the approximately 53 Mt of mill feed underpinning the 30-year production target, approximately
93% is sourced from Indicated Mineral Resources and approximately 7% is sourced from Inferred
Mineral Resources. There is a low level of geological confidence associated with Inferred Mineral
Resources and there is no certainty that further exploration work will result in the determination of
Indicated Mineral Resources or that the production target itself will be realised.
The mine plan has been sequenced such that Indicated Mineral Resources predominate in the early
years of production, with Inferred Mineral Resources weighted towards the later stages of the mine
life. The Company is satisfied that the respective proportions of Inferred Mineral Resources are not
12
the determining factors in project viability and that Inferred Mineral Resources do not feature as a
significant proportion early in the mine plan.
A phased mining approach was developed to prioritise higher-value material and manage
technical risk, commencing with a starter pit that can be mined prior to the full dewatering of the
centre pond from Year 2 to Year 3, followed by two deeper mining phases to a final pit depth of
approximately 240m.
The mine plan targets steady-state production of 1.8Mtpa following a staged ramp-up, with
average total material movement of 2.5Mtpa over the LOM. Waste rock, low-grade material and
topsoil will be strategically stockpiled, with waste rock largely utilised for tailings dyke construction.
Mining fleet requirements and workforce estimates underpin the mining cost model used in the
PEA financial analysis.
Figure 6: Final Pit design
13
Figure 7: Mine Production Schedule.
Figure 8: Crusher feed grades for five payable oxides.
14
Figure 9: Crusher feed by year with contained TREO (%).
15
METALLURGY AND PROCESSING
Minerals Processing Testing and Results
Several mineral processing test work programs have been completed for the Ashram Project to
develop a beneficiation flowsheet capable of producing a rare earth mineral concentrate suitable
for cost-effective hydrometallurgical processing.
The objectives of the various test work programs differed, with some focused on producing a high-
grade mineral concentrate, while others investigated generating a lower-grade concentrate to
maximise REE recovery and produce a fluorspar by-product.
The current beneficiation flowsheet strategy for REE processing is focused on producing a high-
grade mineral concentrate to reduce the complexity and cost of downstream hydrometallurgical
processing. This flowsheet does not consider fluorspar by-products.
Historical metallurgical test work campaigns were undertaken at UVR-FIA GmbH in Germany,
Université Laval in Québec City, Canmet MINING in Ottawa, and Hazen Research Inc. in Colorado,
USA. SGS Canada was subsequently engaged to investigate alternative flowsheets based on the
historical work and the current project objectives.
SGS completed several test programs, including sample preparation, mineral characterisation,
comminution testing, batch and locked-cycle flotation testing, and solid-liquid separation testing.
The SGS work programs formed the basis for the process design criteria and support the
production of high-grade rare earth mineral concentrates.
Hydrometallurgical Testing and Results
Extensive bench-scale and scoping metallurgical test work has been completed to evaluate
hydrometallurgical recovery pathways for the Ashram flotation concentrate and support flowsheet
selection for the PEA.
Early development work by Hazen (Gagnon et al., 2012) successfully demonstrated the production
of commercial-grade mixed rare earth carbonate via a multi-step process incorporating pre-
leaching, magnetic separation, sulphuric acid bake and water leach, selective thorium removal via
solvent extraction, rare earth extraction and purification, oxalate precipitation, and metathesis to
carbonate. High recoveries were achieved across most rare earth elements.
The flowsheet was subsequently simplified, optimised and validated through test work undertaken
by L3 Process Development. Key processing steps were refined and de-risked, demonstrating
effective gangue removal during pre-leach, strong and acid-efficient acid bake performance, and
high water-leach recoveries. Thorium was completely and selectively extracted and recovered
using Cyanex 923 without significant REE losses.
Additional scoping studies assessed alternative processing concepts, including high-activity direct
hydrochloric acid leaching of flotation concentrates.
While it was successful on earlier flotation concentrates, this approach proved sub-optimal on
concentrates generated under the latest flotation flowsheet conditions, reflecting changes in
concentrate grade, mineralogy and impurity levels.
The cumulative test work confirms the technical robustness of the selected recovery flowsheet and
highlights clear optimisation opportunities to be advanced during the Pre-Feasibility Study.
TABLE 4 shows the hydrometallurgical recoveries applied to monazite concentrates fed into the
hydromet plant.
16
TABLE 4: Overall Hydrometallurgical Rare Earth Element Recoveries
Element Hydromet Recovery
Sc 72%
Y 78%
La 77%
Ce 83%
Pr 91%
Nd 91%
Sm 84%
Eu 84%
Gd 84%
Tb 78%
Dy 78%
Ho 78%
Er 78%
Tm 78%
Yb 78%
Lu 78%
On-site Mineral Processing Facility
The Ashram Rare Earth Element Mineral Processing Facility (“MPF” or “concentrator”) will be
located immediately north of the open pit mine. The concentrator will comprise crushing, grinding,
flotation and dewatering circuits.
The facility is designed to process nominal throughput of 4,900 dry tonnes per day (tpd) of run-of-
mine (ROM) mineralised material at an average feed grade of 1.88% rare earth oxide (“REO”),
producing approximately 190tpd of concentrate grading around 30% REO, varying between 28%
and 34% depending on feed grade.
Figure 10: Concentrate tonnes and grade produced onsite at Ashram by year.
0%
5%
10%
15%
20%
25%
30%
35%
40%
0
10000
20000
30000
40000
50000
60000
70000
80000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Grade
Tonnes
Years
Concentrate Tonnes and Grade
Con TREO T Grade %
17
The concentrator is designed to achieve an average REO recovery of 63% based on flotation test
work, although recovery is expected to vary according to feed composition. Filtered concentrate
will be loaded into 20-foot containers and transported south to the hydrometallurgical processing
facility at Saguenay. Concentrator tailings, referred to as processed carbonatite, will be thickened
and pumped to the processed carbonatite storage facility.
Figure 10 above shows concentrator tonnes and grades recovered onsite for shipment to
Saguenay by years.
Hydrometallurgical Processing Facility
The hydrometallurgical processing facility, to be located in Saguenay, will upgrade flotation
concentrate into a Mixed Rare Earth Carbonate (MREC) product using a proven process route
incorporating acid bake, water leach, solvent extraction, oxalate precipitation and metathesis.
The hydromet plant is designed to process approximately 69,500tpa of flotation concentrate and
produce approximately 33,800tpa of MREC, while ensuring effective removal and management of
thorium and other impurities.
Process design is based on preliminary heat and material balance modelling and metallurgical test
work, with individual circuit recoveries resulting in overall rare earth recoveries typically ranging
from approximately 72% to more than 90%, depending on the element.
Comprehensive effluent treatment, scrubbing and reagent management systems have been
incorporated to meet environmental and safety requirements.
Together, the concentrator and hydromet facilities form a technically robust recovery flowsheet that
supports the Project’s production targets and provides a clear pathway from mine feed to a
marketable rare earth product at the PEA level.
Figure 11: MREC production schedule (contained TREO).
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Tonnes
Years
Mixed Rare Earth Carbonate and Contained Total Rare Earth
Oxides by Year
MREC @ 55% TREO TREO
18
INFRASTRUCTURE
The Ashram Project infrastructure strategy is underpinned by a comprehensive transport and
logistics framework designed to support a remote mining operation with limited existing
infrastructure and services in the surrounding region.
A 2025 transport route trade-off study identified a southern logistics corridor as the preferred
development pathway. Under this scenario, concentrate would be transported via a 320km road
link from Ashram to Schefferville, where it would connect to existing rail infrastructure for shipment
to Sept-Îles. From there, containerised concentrate would be transported approximately 570km
either by road or marine transport along the St. Lawrence River to Saguenay.
This intermodal logistics solution is designed to provide reliable, year-round transport while
avoiding reliance on the previously considered northern shipping route, which would have
required construction of new port infrastructure.
Transport logistics consider the naturally present thorium radionuclide content, which becomes
concentrated during mineral processing on site at Ashram. The beneficiate concentrate will leave
the Ashram mine-concentrator site as a class 7 material. During hydrometallurgical processing,
thorium is expected to be concentrated into a separate, stable product (approximate 35% thorium
oxide), while the final MREC product will contain very low thorium levels and is not expected to
trigger radioactive transport regulations. The stable thorium-rich material will be transported
separately to any other product or waste stream for disposal in Saskatoon in a third party approved
and permitted radionuclide storage facility.
Supporting mine site infrastructure includes internal access roads, an aerodrome, diesel-based
power generation, telecommunications systems, fuel storage, explosives facilities, and
administrative and accommodation buildings for a workforce of up to 200 personnel.
Mont Royal is currently exploring options to share the infrastructure development with other local
mining projects, government agencies, and First Nations.